🏁 Final stretch for the Seppi Gaz project !
It's official: the biofilm support material has been received and integrated, and the BioRenGaz installation is now in place ✅
The photos below show the filling of the bioreactor with the biofilm support material inside.
🎯 Objective: double waste recovery capacity in 2 phases
➡️ 5,722 tonnes/year recovered in the first phase with one bioreactor
➡️ 11,445 tonnes/year at full capacity, with two 80 m³ bioreactors
Commissioning is just around the corner, and as a bonus, a magnificent sunset to celebrate the project's progress 🌅